birds eye view of construction workers on site

The Township's Public Works Department manages a variety of construction projects for current and future improvements on Township streets, sidewalks and bridges. Select your project of interest below to learn more.

2024 Guiderail Replacement Program (PW 2024-06)

Status: Detail Design (Updated April 15, 2024)

Contractor: TBD

Consultant: ELLIS Engineering Inc.

Description: Work includes replacement and upgrades to various bridge guiderails.

Approved Budget: $300,000.00

Contract Value:  TBD

Activity: None

Traffic Disruptions: None

Murgatroyd Trail Reconstruction (PW 2024-05)

Status: Detail Design (Updated April 15, 2024)

Contractor: TBD

Consultant: Kerry T. Howe Engineering

Description: Work includes full asphalt replacement, drainage improvements, regrading & flattening of the steep slope, and gabion retaining wall, some lighting improvements.

Approved Budget: $200,000.00

Contract Value:  TBD

Activity: None

Traffic Disruptions: None

Campbell Bridge Rehabilitation (PW 2024-04)

Status: Construction (Updated June 19, 2024)

Contractor: Anthony's Excavating Central Inc.

Consultant: ELLIS Engineering Inc.

Description: Work includes deck rehab, new parapet walls & railings, guiderail repairs, and new asphalt surface.

Approved Budget: $600,000.00

Contract Value:  $448,000.00

Activity: Removals

Traffic Disruptions: Road is closed at the bridge.  Residents on SGR 16 can access their properties from Regional Road 20 only.

2024 Road Rehabilitation Program (PW 2024-01)

Status: Construction (Updated June 26, 2024)

Contractor:  Walker Construction Limited

Description:

Rehabilitation of:

  • Abingdon Road from North Chippawa Road to Concession Rd.
  • Concession 3 Rd from Smithville Rd (RR 14) to Caistor Gainsborough Townline Rd.

Hard topping of gravel road:

  • Vaughan Road from Wellandport Rd (RR 27) to Heaslip Road

Approved Budget: $1,280,000.00

Contract Value: $950,000.00

Activity: Pulverizing & Grading of Vaughan Rd July 2-5, weather dependant.

Traffic Disruptions: Vaughan Rd will be closed daily from 7 AM to 5 PM for the first week of July.  Closure may extend into the 2nd week of July if there are rain days the first week.  Click HERE to view detour route during the road closure.

Barbara St., Brooks Circ., & Killins St. Watermain Replacement, Road Resurfacing, and New Sidewalk (PW 2024-02)

Status: Pre-Construction (Updated May 30, 2024)

Contractor: Catalina Excavating Ltd.

Consultant: Associated Engineering Limited

Description:

Complete watermain replacement, full depth replacement of asphalt surface including some base repairs, some curb replacement, and new sidewalk on Barbara St. and Killins St..

Approved Budget: $1,900,000.00

Contract Value: $1,800,000.00

Activity: None

Traffic Disruptions: None.

 

Public Information Drawings Download (3 MB) PDF File

2023 Road Rehabilitation Program (PW 2023-01)

Status: Substantially completed. Under 1 year maintenance. (Updated January 8, 2024)

ContractorWalker Construction Limited

Description:

Rehabilitation of:

  • Concession 4 Road  from Victoria Rd (RR 20) to Hodgkins Rd.

  • Concession Road 3 from Smithville Rd (RR 14) to Caistor Centre Rd.

  • Young Street from Grimsby Rd (RR 14) to Grassie Rd (RR 8)

  • Industrial Park Road from rail road tracks to Spring Creek Road.

Hard topping of gravel road:

  • Vaughan Road from Wellanport Rd (RR27) to Caistor-Gainsborough Townline Road.

Contract Value: $2,570,000.00

Activity: None

Traffic Disruptions: None.

Pearson Bridge Rehabilitation (PW 2022-02)

Status: Substantially completed.  Under 1 year maintenance. (Updated January 8, 2024)

ContractorAnthony's Excavating Central Inc.

Construction Inspection & Administration: Associated Engineering (Ont) Ltd.

Description: This is a joint project with the Township of Wainfleet.  Work includes deck, ballast wall, and approach slab rehabilitation, including updated guide rail system.

Contract Value: $1,100,000.00

Activity: None

Traffic Disruptions: None