The Township's Public Works Department manages a variety of construction projects for current and future improvements on Township streets, sidewalks and bridges. Select your project of interest below to learn more.
2024 Guiderail Replacement Program (PW 2024-06) |
Status: Detail Design (Updated April 15, 2024) Contractor: TBD Consultant: ELLIS Engineering Inc. Description: Work includes replacement and upgrades to various bridge guiderails. Approved Budget: $300,000.00 Contract Value: TBD Activity: None Traffic Disruptions: None |
Murgatroyd Trail Reconstruction (PW 2024-05) |
Status: Detail Design (Updated April 15, 2024) Contractor: TBD Consultant: Kerry T. Howe Engineering Description: Work includes full asphalt replacement, drainage improvements, regrading & flattening of the steep slope, and gabion retaining wall, some lighting improvements. Approved Budget: $200,000.00 Contract Value: TBD Activity: None Traffic Disruptions: None |
Campbell Bridge Rehabilitation (PW 2024-04) |
Status: Construction (Updated June 19, 2024) Contractor: Anthony's Excavating Central Inc. Consultant: ELLIS Engineering Inc. Description: Work includes deck rehab, new parapet walls & railings, guiderail repairs, and new asphalt surface. Approved Budget: $600,000.00 Contract Value: $448,000.00 Activity: Removals Traffic Disruptions: Road is closed at the bridge. Residents on SGR 16 can access their properties from Regional Road 20 only. |
2024 Road Rehabilitation Program (PW 2024-01) |
Status: Construction (Updated June 26, 2024)
Contractor: Walker Construction Limited Description: Rehabilitation of:
Hard topping of gravel road:
Approved Budget: $1,280,000.00 Contract Value: $950,000.00 Activity: Pulverizing & Grading of Vaughan Rd July 2-5, weather dependant. Traffic Disruptions: Vaughan Rd will be closed daily from 7 AM to 5 PM for the first week of July. Closure may extend into the 2nd week of July if there are rain days the first week. Click HERE to view detour route during the road closure. |
Barbara St., Brooks Circ., & Killins St. Watermain Replacement, Road Resurfacing, and New Sidewalk (PW 2024-02) |
Status: Pre-Construction (Updated May 30, 2024) Contractor: Catalina Excavating Ltd. Consultant: Associated Engineering Limited Description: Complete watermain replacement, full depth replacement of asphalt surface including some base repairs, some curb replacement, and new sidewalk on Barbara St. and Killins St.. Approved Budget: $1,900,000.00 Contract Value: $1,800,000.00 Activity: None Traffic Disruptions: None.
Public Information Drawings Download (3 MB) PDF File |
2023 Road Rehabilitation Program (PW 2023-01) |
Status: Substantially completed. Under 1 year maintenance. (Updated January 8, 2024)
Contractor: Walker Construction Limited Description: Rehabilitation of:
Hard topping of gravel road:
Contract Value: $2,570,000.00 Activity: None Traffic Disruptions: None. |
Pearson Bridge Rehabilitation (PW 2022-02) |
Status: Substantially completed. Under 1 year maintenance. (Updated January 8, 2024) Contractor: Anthony's Excavating Central Inc. Construction Inspection & Administration: Associated Engineering (Ont) Ltd. Description: This is a joint project with the Township of Wainfleet. Work includes deck, ballast wall, and approach slab rehabilitation, including updated guide rail system. Contract Value: $1,100,000.00 Activity: None Traffic Disruptions: None |